Fabrication & Installation
This convey project began in April of 2009. Kinder Morgan is a ship unloading and storage facility located off Meeting St. extension, Charleston. The Limehouse and Sons team fabricated and installed the convey system, which takes Salt from the Ship to the Storage area at the Facility.
10 Man Crew
A job like this requires a large crew of qualified experts in the field. This particular project was assigned a group of 10 Limehouse employees who worked diligently over the 3-month timespan to bring the vision to fruition.
1800
Hours of Work
April-June 2009
Construction Date
10 Man Crew
Manpower
$1.6 Million
Budget
Heavy Equipment
The Kinder Morgan Convey project utilized an array of heavy equipment including our 40 ton,100 ton AND 210 ton cranes. Approximately 1,800 hrs. were spent on this $1.6 million project.