Industrial Construction
This construction project for Longleaf Packaging in Hollyhill, SC began in the winter of 2018 with a completion date spring of 2019.
The crew worked an estimated 2,400 hours on this $250,000 project.
A Great Team
The 6-man crew helped in the construction of many facets of the facility, which will package cement and mortar mix.
The completed facility is state-of-the-art, with a robotic arm that sorts each bag and stacks them neatly on to pallets. There are silo’s for storage, conveyors for transporting raw materials and a rotary dryer for drying the sand and rock. We are proud to be part of this project!
Hours of Work
Construction Date
Manpower
Budget